A supplier says a flood excuses all delivery obligations, but it had missed two deadlines before…
A supplier says a flood excuses all delivery obligations, but it had missed two deadlines before the flood. The contract has a force-majeure clause. Does it excuse everything?
Answers & Replies
1Not automatically. The clause’s wording determines which events are covered, whether the event must prevent or merely delay performance, what notice and mitigation duties apply, whether alternative sourcing is required, and what happens after a specified period. The pre-flood delays may have an independent contractual explanation or constitute a separate breach. Preserve purchase orders, schedules, notices, evidence of the flood’s impact, and correspondence. Ask the supplier for the clause relied on, supporting evidence, mitigation steps, and a realistic recovery schedule. Check suspension, termination, substitute procurement, damages, and notice provisions carefully. A lawyer should apply the clause to the actual facts; the phrase ‘force majeure’ does not decide the dispute by itself.